COLUMBUS, Ind. – The City of Columbus says crews will begin Phase 1 of the overlay project this week.
No on-street parking will be allowed and any cars left parked on the street will be towed.
Approximate work times will be from 7 a.m. to 7 p.m. Monday thru Friday. Dave O’Mara Contractors will begin work in McCullough’s Run and Prairie Streams and then move to Windsor Place and Oakbrook at Tipton Lakes.
Visit the city’s engineering page for a detailed list of streets: https://www.columbus.in.gov/engineering/.
Here is the city of Columbus overlay schedule for this week and next:
McCullough’s Run
Patching starts on or after May 17
Milling begins on or after May 19
Surfacing commences on or after May 20
Prairie Streams
Patching begins on or after May 19
Milling starts on or after May 24
Surfacing commences on or after May 25