COLUMBUS, Ind. - The City of Columbus has announced that beginning Tuesday, September 1, and continuing through Tuesday, September 8, crews will ramp up work on water main and storm sewer improvements on Second Street, between Jackson and State Streets.
The project will require temporary road closures and lane restrictions. Most traffic impacts are expected to occur overnight to reduce disruptions for motorists.
On Tuesday, Sept. 1, workers will line-stop the 8‑inch water main at Second and Washington Streets and retire the section of the main serving the east end of Second Street. Once it is retired, crews will install a new storm sewer inlet at Sycamore Street.
On the evening of Tuesday, Sept. 8, crews will install a 36‑inch storm sewer across Second Street. During this work, Second Street will be closed at Jackson Street. The installation is expected to take one night. While the street is closed, traffic will be rerouted north on Jackson Street or south on First Street to Franklin Street.
Drivers are encouraged to use caution in the area, follow posted detours, and expect periodic delays throughout the project period.
The completion timeline is weather-dependent. Inclement weather may delay progress within the designated schedule.
'Never Forget' - 2026 Patriot Day Observance in Columbus is Friday
Columbus City Administration proposes new staffing positions in 2027 Civilian Salary Ordinance
Edinburgh Fire and Rescue gets new watercraft
Landmark Columbus Foundation reaches goal for endowment fund
Columbus East grad receives scholarship from Association of Indiana Counties