FRANKLIN, Ind. — The City of Franklin Board of Public Works and Safety has approved a noise ordinance variance to allow nighttime construction along the US 31 corridor to help secure the route for winter travel.
Milestone Contractors presented the request to allow overhead signal and signage work between 7 p.m. and 7 a.m.
Construction on Phase 3 has fallen behind its original August 1 completion deadline. Due to extensive utility relocation delays across the corridor, final phase completion has been pushed back to June 2027.
To mitigate further delays and improve safety before winter weather sets in, Milestone has implemented weekday overtime and Saturday shifts. The approved evening hours will enable crews to complete overhead spans and signal work over US 31 with minimal disruption to daytime traffic.
BCSO arrests wanted man after I-65 welfare check
Smoke alarm alerts Columbus family to early morning house fire
Several Bartholomew County Roads temporarily closed next week
Ivy Tech Columbus joins nationally recognized Metallica Scholars Initiative
Begin your Small Business Saturday shopping at Franklin Chamber's 'Start Here Open House'