Unmapped infrastructure delays 2nd Street Thoroughfare Project completion until late October

Courtesy-City of Columbus

COLUMBUS, Ind. - Drivers navigating downtown Columbus can expect ongoing lane restrictions as crews work through underground delays on the 2nd Street Thoroughfare Project.

City officials report that crews with Dave O'Mara Contractor, Inc. have continually encountered century-old, unmapped utility infrastructure beneath the roadways.

Work at the Franklin Street intersection recently revealed an unmapped, operational utility main, requiring overnight crews to excavate between 9 p.m. and 5 a.m. to minimize traffic disruptions.

Contractors say most work will finish in late October, with final street landscaping to follow shortly after. The city has also finalized traffic staging and safety routes with organizers of the upcoming Ethnic Expo to ensure festival operations run smoothly around active construction areas.

Motorists are encouraged to use alternative downtown routes and exercise caution near work zones.

More from Top Stories

Community Calender

  • Columbus North Fall Choir Concert

    Join us at Columbus North High School at the Erne Auditorium for our Fall Choir Concert featuring Vocal Pointe, North Stars, Northern Lights, 25th Street Jazz

  • 2026 Taste of Columbus

    ✨ Save the Date: Taste of Columbus 2026 ✨ 📅 Wednesday, October 7, 2026 📍 The Commons | Downtown Columbus ⚠️ Ages 21+ (Valid ID Required)

    at The Commons
  • Taste of Columbus 2026

    Taste of Columbus 2026! 🍴 Oct. 7, 5–8 PM at The Commons. Enjoy local bites, drinks, live music, a silent auction & more! Ages 21+. Tickets $35.

    at The Commons

Today's Weather

  • Bartholomew County Weather

    Sunny

    High: 81°F | Low: 52°F

Follow Local News Digital on